City of Mirabel

Municipal Sector

General contractor
Process mechanics
Year of completion: 2014
Location: City of Mirabel
Value of work: $1 million

Rehabilitation/increase in capacity of the Victor pumping station.


Challenges Met

Installation of a pumping station with a cage and a filtering tip.

Demolition of 60 MPA of concrete in a confined space over 35 feet deep.

photosgrand_projetsmirabel

Description of the Project

  • Replace 125 HP submersible pumps without interrupting services.
  • Installation of a new control center, including variable speed drives (VFD).